3 Nukes Shutting Down

Wednesday, April 25, 2018 @ 10:04 AM gHale

FirstEnergy Solutions is moving to deactivate three nuclear plants in Ohio and Pennsylvania over the next three years.

The company, a subsidiary of FirstEnergy Corp., filed a Certification Letter with the U.S. Nuclear Regulatory Commission (NRC) saying it will permanently deactivate its nuclear power plants over the next three years, citing “severe economic challenges.”

RELATED STORIES
NRC OKs 2 New Reactors in FL
Feds Hit Entergy for Nuke Plant Violations
Assessments Issued for Nation’s Nukes
NM Nuclear Fuel Storage Site Begins

The letter affirms the company’s March 28 notification to PJM Interconnection (PJM), the regional transmission organization, as well as its initial, informal notification to the NRC. The plant closures are subject to review by PJM for reliability impacts.

Up until the closures, the plants will continue normal operations.

“We are actively seeking policy solutions at the state and federal level as an alternative to retiring these plants, which we believe still have a crucial role to play in the reliability and resilience of our regional grid,” said Don Moul, president of FES Generation Companies and chief nuclear officer. 

“What also is at stake for the region is 4,048 megawatts of zero-emission baseload generating capacity, an all but irreplaceable resource,” he added. “As early as mid-2019, we will begin facing decisions on each of these plants as to whether to refuel them or shut them down. Absent legislative or regulatory relief, we cannot continue to operate the plants on their current uneconomic basis.”

FES, its subsidiaries and FirstEnergy Nuclear Operating Company on March 31 filed petitions under Chapter 11 of the Federal Bankruptcy Code in order to facilitate an orderly financial restructuring. The case is proceeding in U.S. Bankruptcy Court for the Northern District of Ohio, in Akron.

The retirement schedule of the nuclear plants is as follows:
• Davis-Besse Nuclear Power Station, Oak Harbor, Ohio, by May 31, 2020
• Beaver Valley Power Station Unit No. 1, Shippingport, PA, by May 31, 2021
• Perry Nuclear Power Plant, Perry, Ohio, by May 31, 2021
• Beaver Valley Power Station Unit No. 2, Shippingport, PA, by October 31, 2021

The closure of the plants will affect about 2,300 plant employees.

The total capacity of the nuclear plants to be deactivated is 4,048 megawatts (MW). In 2017, the nuclear units contributed approximately 65 percent of the electricity produced by the FES generating fleet. The two nuclear plants in Ohio represent 14 percent of the state’s overall generation capacity; the Beaver Valley units represent 7 percent of Pennsylvania’s overall generation capacity.