Enbridge Must Dig Deeper for MN Pipeline Plan

Friday, September 6, 2013 @ 02:09 PM gHale


Enbridge Energy’s pipeline expansion plans need deeper study, Minnesota regulators decided Wednesday.

Enbridge wants to install new pumps to an existing line that brings oil from the tar sands in Alberta, Canada, across northern Minnesota to a refinery in Superior, WI. The new pumps would boost flow in the Alberta Clipper line to its 800,000 barrel-a-day capacity.

RELATED STORIES
New Pipeline Opens East Coast
Enbridge Pays to Build Bigger Pipeline
MI Utility Pays for 2 Gas Line Blasts
IL Pipeline Blast under Investigation

In July, the Minnesota Public Utilities Commission approved a smaller expansion. On Wednesday, though, commission members agreed with the state Commerce Department they need to see further study.

The issue now goes to an administrative law judge. The study could take as much as a year.

The Commerce Department said the application did not provide enough documentation of the need for the expansion, and did not prove it would benefit the people of Minnesota or neighboring states.

In 2010, an Enbridge pipeline in Michigan burst and spilled more than one million gallons of Canadian crude into the Kalamazoo River. Cleanup is not yet completed.

Enbridge says it’s ready to provide answers during the review process.

The Alberta Clipper was put in service with a capacity of 450,000 barrels per day, with the ability to increase to 800,000 should the demand arise, Enbridge spokeswoman Lorraine Little said.

“That demand or that need from shippers has arisen, so that’s what this project is about, providing North America with access to North American crude oil,” Little said.

The year-long construction would employ about 100 workers, she added.