Enbridge Energy Partners LP can now restart its Line 14, which leaked more than 1,000 barrels of oil in Wisconsin in July, after the Department of Transportation (DoT) gave its approval.

The federal agency said Enbridge agreed to extra safety precautions before restarting the 467-mile line, including restricting line pressure to 80% of that used at the time of the July 26 failure.

RELATED STORIES
Enbridge Line Fixed, Flow on Hold
U.S. Blocks Pipeline Restart
Oil Pipeline Valve Fails Test
NTSB: Neglect Cause of MI Oil Spill

The leak at Grand Marsh, WS, was the third major spill at an Enbridge pipeline, including a 20,000-barrel leak at a line in Michigan in July 2010 that ultimately resulted in a $3.7 million civil penalty against the company.

The 317,600 barrel-a-day Line 14 carries light crude oil to Chicago-area refineries, accounting for about a fifth of the oil imported into the region. Its outage was not as bad as it could have been because there were issues due to mechanical problems at refineries operated by BP PLC and Citgo Petroleum that cut demand for oil.

Enbridge Energy Partners is a Houston-based affiliate of Calgary-based Enbridge Inc. The U.S. Pipeline and Hazardous Materials Safety Administration prevented Enbridge from restarting Line 14 until the company made repairs at the leak site.