Hanford Outage Extended; Clean Up Begins

Friday, August 5, 2011 @ 02:08 PM gHale

A delay in replacing a key piece of equipment at the nuclear plant on the Hanford nuclear reservation extended its outage into September.

While the nuclear plant delay is three months longer than planned and could cost more than $60 million in lost power production, officials are getting a jump on digging up one of the most hazardous waste burial grounds at Hanford.

RELATED STORIES
Radioactive Pond too ‘Hot’ to Test
EU Nuclear Waste to go in Secure Bunkers
Nuclear Fallout: Toxic Waste Storage Switch
Nuclear Safety Plan: From Cradle to Grave

The 26-year-old Columbia Generating Station shut down April 6 for a planned 80-day outage for refueling and to replace the condenser, which turns steam back into water. Officials extended the outage in July.

The Energy Department’s John Dobken said most of the 1,800 workers involved in the refueling part of the work have already left the Hanford site.

Meanwhile, digging is under way on the waste burial grounds at Hanford.

There is a delay in starting up the nuclear plant in Hanford, but clean up started on one of the most hazardous waste burial sites around.

There is a delay in starting up the nuclear plant in Hanford, but clean up started on one of the most hazardous waste burial sites around.

“We expect to find up to 2,000 drums containing everything from mildly contaminated clothing and debris to highly radioactive laboratory equipment and liquids,” said John Darby, the Washington Closure Hanford remediation project manager for the 618-10 trenches.

Excavation at the 618-10 Burial Ground started with its 12 trenches, and planning is under way to safely remove 94 vertical pipe units there. The vertical pipe units, made of five bottomless 55-gallon drums welded together and buried upright, were a dump for highly radioactive wastes.

In excavating the trenches, workers already have uncovered about 30 55-gallon drums that enclose pipes surrounded by concrete. The concrete-lined drums typically disposed of radioactive liquids.

Workers also have found 200 bottles containing liquids, which they will have to evaluate and treat before disposal.

That’s in addition to about 30 excavated drums that contain radioactively contaminated shavings in oil and miscellaneous debris, Darby said. Oil went in some drums disposed at Hanford to keep uranium shavings or other material from igniting if exposed to oxygen.

Disposal records for the 618-10 Burial Ground, used from March 1954 until September 1963, are incomplete. But officials know it contains radioactively contaminated equipment and samples from research at Hanford. That could include contaminated laboratory instruments, bottles, boxes, filters, aluminum cuttings, irradiated fuel element samples, metallurgical samples and electrical equipment.

The Department of Energy faces a legal deadline to have the 618-10 Burial Ground cleaned up by 2018, but would like to have most environmental cleanup work completed in the 220 square miles along the Columbia River by fall 2015.

The start of the 618-10 project accelerated because of federal economic stimulus money, said Mark French, DOE’s project director for the Columbia River corridor.

DOE is spending $57 million of Hanford’s American Recovery and Reinvestment Act money to get a good portion of the work done. Already that money has paid for two years of preparation to allow for the safe start of excavation of the trenches on the six-acre site.



Leave a Reply

You must be logged in to post a comment.