More Woes at San Onofre Nuke

Thursday, May 31, 2012 @ 05:05 PM gHale


San Onofre nuclear power plant in California operated for decades with equipment that might have temporarily severed the plant’s emergency power supply in the event of an earthquake.

That disclosure by Southern California Edison about a possible backup power problem comes during a probe into excessive wear on tubing that has kept the seaside plant shut down for nearly four months.

RELATED STORIES
Condenser Causes Pilgrim Shut Down
River Bend Reactor Scrams
New Nuke Regulations Pass Quietly
CA Nuke Retires Worn Tubes

The company disabled the emergency power supply equipment — a vibration sensor — and reported the issue to federal regulators as “an unanalyzed condition that significantly degraded plant safety.” Edison said other back-up systems were in place during that time.

“Engineers are continuing to analyze the condition and have not reached a final conclusion if the sensor would actually cause a shutdown during an earthquake,” company officials said in a statement.

A steady supply of electricity is a critical issue at nuclear plants, which need power to ensure reactors do not overheat like they did in Japan. That is when a tsunami destroyed backup generators at the Fukushima Dai-ichi nuclear power plant — setting off the world’s worst nuclear disaster since Chernobyl.

At issue at San Onofre is a vibration sensor in use since 1981 on emergency diesel generators, which start if the plant’s outside power ends up cut off — a possibility during an earthquake.

Engineers found the sensor — designed to protect components inside the generators during operation — might incorrectly stop them during an earthquake.

Edison engineers are looking into whether “high vibration … could interrupt the onsite electrical generation” during a temblor, according to records filed with the Nuclear Regulatory Commission.

If the generators fail, the plant can use battery power for up to four hours to operate the steam generators to cool the twin reactors.

The plant between Los Angeles and San Diego has been idle since January while investigators try to determine why tubing that carries radioactive water in relatively new steam generators eroded at an unusual rate, in some cases rapidly.

Gradual wear is common in such tubing, but the rate of erosion in some tubes at San Onofre alarmed officials since the equipment is relatively new. The company it will take 1,300 tubes out of service, although the number is well within the margin to allow the generators to keep operating.

Edison initially targeted a June restart for at least one of the twin reactors, but that appears increasingly unlikely as investigators continue to review the widespread problem.



Leave a Reply

You must be logged in to post a comment.