VT Nuke: Failed Flood Seals

Friday, March 29, 2013 @ 06:03 PM gHale


The woes continue at Vermont Yankee nuclear plant as a failed underground flood seal last week compromised the flooding-prevention design of a nerve center where cables from the plant’s control room route to the rest of the plant.

The problems required formal notification to the Nuclear Regulatory Commission (NRC).

Vermont Yankee has been shut down since March 9 for refueling and maintenance work, and the problems ended up partly triggered by maintenance work.

RELATED STORIES
Prairie Island Nuke Turns White
After Pump Failure, IL Nuke On Line
NRC: Upgrade Reactor Vents
San Onofre Can Run Safely, for a Bit

While the switchgear room was not in a flooded state, the two feet of water in a manhole in the room ended up discovered because the manhole cover was off to allow preparatory work on a new replacement auxiliary transformer, said Neil Sheehan of the NRC.

Robert Williams, a spokesman for Entergy Nuclear, owner of Vermont Yankee, said the switchgear rooms are where the cables from the control room route on their way to the other parts of the plant. The design of the rooms call for earthquake protection, as well as fire protection and access controls, he said.

No electrical equipment suffered any type of flooding, he said.

“The water intrusion was identified and resolved immediately,” Williams said.

Chris Recchia, commissioner of the Department of Public Service, said the issue is important from a policy standpoint because Vermont Yankee had replaced faulty flood seals after Tropical Storm Irene.

“We need to wait for their report and see if it’s a newer problem or an older problem,” Recchia said.

If it had been a regular flood, “there could have been serious damage,” he said. “Clearly the system, and the seal, were not functioning well. Whether it was one of the new seals or an old seal, I don’t know.”

Sheehan said the problem started last week when workers, who were cleaning out the Connecticut River water intake structure at the plant, placed watery silt on land adjacent to a manhole. The watery silt created a “ponding” effect, and the water ran off into the manhole, he said.

That manhole cover seal failed, letting the silty water into the conduit system, and it eventually made its way via a “displaced” conduit pipe seal to a manhole in the switchgear room, Sheehan said.

The water came up two feet in the manhole in the switchgear room, but sump pumps removed the water. The manhole itself is eight feet deep.

“The level of water inside the switchgear room manhole was less than 2 feet at all times and remained well below the level of the switchgear room floor,” Sheehan said.

Uldis Vanags, the state nuclear engineer, said in a memo to the Vermont State Nuclear Advisory Panel that Entergy had to submit a licensee event report to the NRC within 60 days of their identification of the degraded flood seal.

“Vermont Yankee has entered this event into their corrective action program and is conducting a cause investigation,” Vanags said.

Williams said the water traveled about 400 feet from the dredging near the intake structure to the switchgear rooms. He said the water did not contact the contaminated areas and was not radioactive.

Sheehan said after they discovered the water, Yankee personnel began inspecting outside manholes and Saturday discovered the mechanical seal that had become “displaced,” which allowed the water to flow from the outside manhole into the switchgear room manholes.

He said workers initially reinstalled the seal, but Yankee workers put a new foam seal in place Sunday.

Williams said the failed conduit seal, which did have a mechanical seal threaded into place, ended up replaced with a better design “to preclude a similar situation in the future.”

Sheehan said the NRC was continuing its post-Fukushima assessment of flooding risks at all nuclear power plants, and the seal’s design to prevent flooding remains an area of focus.



Leave a Reply

You must be logged in to post a comment.