Seven workers ended up treated for minor smoke inhalation on scene, said officials at the Chattanooga Fire Department.
It was a mass exodus, with thousands of VW employees stopping work and rushing outside. There was smoke over the roof as emergency vehicles rushed to the scene.
“As we were preparing to ship our truck out and load it, the fire alarms went off,” said Keith Gattis, a contractor who works at the Volkswagen plant said in a published report.
Bennett was in the body shop where the fire happened. He said the employees worked together and did the best they could to handle the situation.
“We were trying to extinguish as much as we could to try to keep production moving, and it was just getting out of hand,” Bennett said.
In a release sent later in the day, the Chattanooga Fire Department said a conveyor belt in a confined space had caught fire. Investigators are still working to learn exactly what caused the fire.
“These types of fires are extremely dangerous. Life hazard is our primary concern with so many employees working there. We rely heavily on Volkswagen’s team for accountability and they do a great job with that,” said Fire Chief Phil Hyman. “Time is everything for us in these situations so having an on-site fire department is a huge help. Our relationship with VW is strong and we worked very well together.”
Around 4,000 employees ended up forced to evacuate the plant, a VW spokesperson said.
It took firefighters about 30 minutes to get the blaze under control. Crews spent the aftermath dealing with smoke and water damage along with hazardous materials that were in the body shop.
VW spokeswoman Amanda Plecas said sprinklers went off on the affected line and contained the fire.
Firefighters encountered heavy smoke, but the natural ventilation from the bay doors at the body shop allowed them to have some visibility. With flames under control, firefighters then monitored hot spots, officials said.
Ventilation fans cleared out smoke in the building and booms prevented water runoff into other areas of the structure.
Plecas said the company planned to resume operations at the site Wednesday.
This short-term shutdown comes after a nationwide chip shortage caused the plant to suspend production earlier this year. A Volkswagen spokesperson said Chattanooga production shuts down for two weeks this year, most recently in June.