After a decommissioning process, the license for the Humboldt Bay Power Plant, Unit 3, in California ended up terminated and the site has now been released for unrestricted use.

The termination by the Nuclear Regulatory Commission (NRC) comes after Pacific Gas & Electric Co. successfully decommissioned the facility to meet radiation protection standards.

Humboldt Bay Unit 3 was a boiling water reactor operated by PG&E from 1963 to 1976.

Units 1 and 2 at the site, located 4 miles from Eureka, CA, in Humboldt County, were fossil fuel power plants previously decommissioned. PG&E currently operates a separate fossil fuel plant adjacent to the site.

Unit 3’s independent spent fuel storage installation will remain under a separate NRC license.

Schneider Bold

PG&E remains responsible for the security and protection of the storage facility and is required to maintain $53.3 million in liability insurance coverage until the fuel has been removed from the storage facility site. PG&E also is responsible for safely decommissioning the storage facility site once the fuel is gone.

PG&E submitted final status surveys of the Unit 3 site and requested license termination in October. The NRC staff evaluated the surveys, conducted inspections, and reviewed confirmatory analyses before concluding the site meets NRC criteria for license termination for unrestricted use.