Holtec and HDI said they intend to expedite the decommissioning and dismantling of the power plant, according to a report with the Nuclear Regulatory Commission (NRC).
Indian Point’s three pressurized-water reactors are in Buchanan, NY, 24 miles north of New York City. Units 1 and 2 are permanently shut down; Unit 3 is on schedule to permanently shut down in April 2021. The license transfer also includes the plant’s dry cask spent fuel storage installation.
In reviewing the license transfer application, the NRC staff considered the Holtec and HDI technical and financial qualifications. It also looked at the adequacy of the Indian Point decommissioning trust funds to complete the radiological decommissioning of the plant. In addition, it looked at the adequacy of plans to manage the onsite storage of spent nuclear fuel until it can end up removed for storage or disposal elsewhere.
The NRC staff concluded Holtec and HDI met the regulatory, legal, technical and financial requirements necessary to qualify as licensees.