Just a bit under a year ago on 24 April 2021, a lift boat (L/B) was performing plugging and abandonment work next to a fixed facility, when the L/B crane operator notified the contract supervisor because of rough seas they were going to have to raise the L/B.
After a toolbox talk with all personnel, the crane operator started slacking off a few feet of the L/B crane’s load line because it was attached to a wellhead via 4.1-ton dual slings, according to the BSEE report.
After the talk with all personnel, the crane operator then informed the first mate it was okay to change the hydraulic system over to operate the legs of the L/B. According to the incident report, the L/B’s crane has no hydraulic pressure during the lifting/lowering operations, which renders the hydraulic controls systems inoperable, preventing any adjustments to the crane’s position or load lines.
That is when the crane operator exited the crane cab and went to help the contract supervisor on deck, leaving no one to monitor the crane’s load line and slings, according to the report. The L/B rose approximately two feet when it is suspected the slings caught on the wellhead hanger pins and snapped, striking, and injuring the well service operator.
As a result of the incident, the BSEE recommends operators consider:
- Disconnecting all platform L/B interface connections during L/B jacking operations, including crane load line(s) and gangways
- Ensuring the connected rigging hardware is free and clear when the crane’s load line is attached to component and before changing elevations
- Reminding crane operators they need to remain attentive, in control, and in the crane cab while attached to a load to ensure a safe and successful crane operation
- Adopting a Standard Operating Procedure for L/B elevation adjustments during operations
- Developing policy/procedure to require a Job Safety Analysis to be conducted for when a L/B needs to be raised or lowered during well work or construction activities
- Ensuring all hazards are identified and addressed in JSA before and during the operation, especially L/B and platform/well interconnect and interface hazards
- Removing the gangway before raising or lowering a L/B
- Ensuring L/B cranes are operating within crane manufacturer’s parameters with all systems functioning properly

An incident on a lift boat occurred when slings on a crane caught on the wellhead hanger pins and snapped, striking, and injuring the well service operator.
Source: BSEE