The River Bend nuclear power plant is going to undergo a review so federal officials can understand the circumstances related to the failure of five portable emergency diesel generators during testing.

Entergy Operations operates the facility in St. Francisville, Louisiana.

The generators in question are used to supply power to plant systems in the event of a prolonged loss of off-site electrical power coupled with a failure of the permanently installed emergency generators, said officials at the Nuclear Regulatory Commission (NRC).

These portable generators ended up acquired as part of the facility’s safety enhancements mandated by the NRC following the 2011 accident at the Fukushima Dai-ichi facility in Japan.

Schneider Bold

The three-member NRC team will develop a chronology of the test failures and evaluate the licensee’s causal analyses and the adequacy of corrective actions.

Because of the COVID-19 pandemic, they will complete most of their work remotely. An inspection report documenting the team’s findings will be publicly available within 45 days of the end of the inspection.

Pin It on Pinterest

Share This