An application to renew for 20 years the previously renewed operating licenses of Point Beach Nuclear Plant Units 1 and 2 ended up accepted by the Nuclear Regulatory Commission (NRC).

NextEra Energy submitted the license renewal application on Nov. 16. The application, without proprietary details, is available on the NRC website.

NextEra is seeking a subsequent renewal for the Point Beach units, in Two Rivers, Wisconsin, located 13 miles northwest of Manitowoc. The NRC approved the initial license renewal in December 2005, with Unit 1 currently licensed to operate through Oct. 5, 2030, and Unit 2 through March 8, 2033.

NextEra renewal for PBN Unit 1 and Unit 2 for a period of 20 years beyond the expiration of the current renewed operating licenses. This would extend the renewed operating license for PBN Unit 1 from midnight on October 05, 2030, to midnight October 05, 2050, and PBN Unit 2 renewed operating license from midnight on March 08, 2033, to midnight on March 08, 2053, according to the application.

Units 1 and 2 employ a pressurized water nuclear steam supply system (NSSS) with two coolant loops furnished by the Westinghouse Electric Corporation. Each reactor was originally designed to produce a core thermal power output of 1519 megawatts-thermal (MWt) with a corresponding gross electrical output of 524 megawatts-electric (MWe) each. Commercial operation for Unit 1 began on October 05, 1970 and for Unit 2 on March 08, 1973.

Schneider Bold

Since being placed into commercial operation, each unit has undergone a low pressure turbine retrofit modification that increased the gross electric output to 538 MWe. In addition, a measurement uncertainty recapture (MUR) power uprate was implemented for both units. The MUR uprate increased the license reactor core thermal power for each unit to 1540 MWt and turbine generator electric output to approximately 545 MWe.

Accepting the application for review, or “docketing” it, does not indicate whether the Commission will approve or reject the request.

More information regarding subsequent license renewal is available on the NRC website.

The NRC has published in the Federal Register a notice of opportunity to intervene in an adjudicatory hearing. Petitions to intervene in a hearing must end up filed by March 23 by anyone whose interest may be affected by the proposed license renewal and who wishes to participate as a party in the proceeding.