The NRC scheduled a regulatory teleconference with Entergy to discuss the apparent violations identified in an Oct. 29 inspection report related to Grand Gulf’s radioactive materials transportation program. No decision on the final safety significance of the apparent violations or any NRC actions will be made at the meeting.
On August 21, the NRC completed an inspection to review the details of the May 22 transport of radioactive licensed material from the site to a processing facility in Oak Ridge, Tennessee.
In what investigators are saying is a violation, NRC investigators said Grand Gulf staff transported a radioactive material package described as Low Specific Activity (LSA) – II that failed to meet the radiation level limits. The measured radiation levels were in excess of 10 mSv/hour (1 Rem/hour) at 3 meters from the unshielded package, exceeding the conditions of transport for LSA material and requiring the package end up labeled as Type B radioactive material. Consequently, the shipment failed to contain the appropriate emergency response information as well as the appropriate package markings.
In addition, the NRC said the finding has four associated apparent violations under consideration for escalated enforcement action in accordance with the NRC Enforcement Policy.
Because the NRC has not made a final determination in this matter, it did not issue a notice of violation.