After FirstEnergy, and its affiliates, completes its bankruptcy proceedings, transfer of operating licenses for the Beaver Valley Units 1 and 2, Davis-Besse and Perry nuclear power plants and associated spent fuel storage installation facilities will move over to Energy Harbor Corp., Energy Harbor Nuclear Generation LLC and Energy Harbor Nuclear Corp., federal officials said.
The transfer will become effective upon completion of the bankruptcy and the formation of Energy Harbor Corp., which will wholly own Energy Harbor Nuclear Generation LLC and Energy Harbor Nuclear Corp. Beaver Valley Units 1 and 2 are pressurized-water reactors located approximately 17 miles west of McCandless, PA.
The units are scheduled to permanently shut down in May 2021 and October 2021, respectively.
Davis-Besse is a pressurized-water reactor located approximately 21 miles southeast of Toledo, Ohio, and is licensed to operate through April 22, 2037.
Perry is a boiling-water reactor located approximately 35 miles northeast of Cleveland and is licensed to operate through March 18, 2026.
In Ohio, 2019’s House Bill 6 has thrown the Davis-Besse plant near Toledo and the Perry plant a lifeline in the form of a $150 million-a-year, taxpayer-funded bailout that extends for seven years.
The NRC staff’s review of the license transfer application concluded Energy Harbor Nuclear Generation LLC is financially qualified to own Beaver Valley, Davis-Besse, and Perry, and that Energy Harbor Nuclear Corp. is financially and technically qualified to operate the plants.
The NRC staff also concluded, since the plants’ existing decommissioning funds will be transferred, the new licensees satisfy the NRC’s decommissioning funding assurance requirements and the facilities are not owned, controlled, or dominated by a foreign entity.
FirstEnergy Solutions (FES), which is a part of FirstEnergy, said at the end of November that it will change its name to Energy Harbor when it exits bankruptcy and is no longer attached to its parent, FirstEnergy Corp.