A special inspection this week will evaluate the cause of a radiation release and worker contamination at the National Institute of Standards and Technology’s (NIST) research reactor in Gaithersburg, MD, federal officials said.

There was an emergency Feb. 3 during startup of the reactor, where radioactive material was released inside the reactor building, in a NIST notification to the Nuclear Regulatory Commission (NRC).

Six workers ended up initially contaminated during the event, and four additional workers were mildly affected while responding later in the day. All the workers underwent decontamination and return home the same day. While a small amount of radioactive material reached the environment, available information continues to show the public near the NIST facility remains safe, as the release was under regulatory limits.

NIST said a radiation alarm was triggered on its Gaithersburg campus around 9:15 a.m. Feb. 3 during a restart of a neutron research reactor following routine maintenance.

Several workers suffered exposure to the elevated radiation levels during the restart and are undergoing decontamination and evaluation, according to a statement from the NIST Center for Neutron Research. Staff immediately initiated a shutdown of the reactor.

Schneider Bold

“All systems appear to have worked as designed and all protocols were followed in a timely manner,” NIST said in a release.

The reactor is housed in a confinement building on NIST’s Gaithersburg campus. The laboratory describes that building as a special area designed to contain radioactive materials, with equipment including a filtered ventilation system.

Two inspectors from NRC headquarters in Rockville will begin this inspection Tuesday, supplemented with additional inspectors as needed.

They will evaluate the adequacy of NIST’s response to the situation, NIST’s determination of the root cause of the event and NIST’s corrective actions. The inspectors will also review radiation monitoring data and determine if there are generic implications for similar facilities.

The inspectors will follow all applicable guidelines related to the COVID-19 public health emergency during their activities.

The inspectors will prepare a written report that will be issued approximately 30 days following completion of the inspection.