The final well control rule from the Bureau of Safety and Environmental Enforcement (BSEE) builds upon the regulatory reforms implemented after the 2010 Deepwater Horizon explosion and resulting oil spill that killed 11 people and caused billions of dollars in environmental damage and economic loss to coastal communities.
“Finalizing this rule will enable BSEE to continue to put the lives and livelihoods of workers first, as well as the protection of our waters and marine habitats,” said BSEE Director Kevin Sligh. “This rule strengthens testing and performance requirements for blowout preventers and other well control equipment, provides for timely and robust analyses and investigations into failures, and clarifies reporting requirements to ensure we have appropriate visibility over information and data critical to maintaining well integrity.”
Right after the Deepwater Horizon incident, BSEE adopted several recommendations from multiple investigation teams to improve the safety of offshore energy operations, leading to the publication of the 2016 Well Control Rule.
In May 2019, BSEE published a final rule that weakened certain safety provisions. Today’s final rule incorporates key lessons learned from operator experience, incident data regarding blowout preventers, and well integrity since the publication of the 2016 rule and revises or rescinds certain modifications made in the 2019 rule.
Department of the Interior finalized revisions that will:
- Require blowout preventer systems (BOPs) to be able to always close and seal the wellbore to the well’s maximum anticipated surface pressure, except as otherwise specified in the BOP system requirement section of the regulations
- Require failure data reporting to a designated third party and BSEE
- Require failure analysis and investigations to start within 90 days of an incident
- Require independent third-party qualifications to end up submitted to BSEE with the associated permit applications
- Specify surface BOPs on existing floating facilities must follow the dual shear ram requirements when replacing an entire BOP stack
- Require remotely operated vehicles be capable of opening and closing each shear ram on a BOP
- Require the operator to provide BOP test results to BSEE within 72 hours after completion of the tests if BSEE is unable to witness testing
Click here to review the final well control rule.