Purdue notified the Nuclear Regulatory Commission (NRC) earlier this month of an error during calibration of newly installed nuclear instrumentation, resulting in the reactor operating significantly above its licensed power level at times during the past few months.
An inspector from the agency’s headquarters in Rockville, MD, along with an inspector from the Region III office in Lisle, IL, began the inspection Tuesday. They will evaluate the adequacy of Purdue’s response to the situation, the root cause of the problem, corrective actions, radiation monitoring data, and determine if there are generic implications for similar facilities.
Available information shows the health and safety of the facility’s staff and the public remained unaffected by the unplanned excess power levels. Available information also shows the excess power stayed well below levels that could have damaged the reactor’s fuel or safety systems.
The inspectors will spend several days at Purdue and prepare a written report that will be issued 30 days following completion of the inspection. The report will be publicly available through the NRC’s electronic document database, ADAMS.