A special inspection launched at the Urenco USA uranium enrichment facility in Eunice, New Mexico, in an effort review the circumstances involving a March 2 event during which construction vehicles entered a controlled area before appropriate physical barriers were in place, federal officials said.

The facility remains safe, and the incident did not result in an increased risk to public health and safety. The event warrants additional Nuclear Regulatory Commission (NRC) inspection because it involved a potential breakdown of controls designed to prevent chemical, radiological, and criticality hazards – the primary concern at U.S. fuel cycle facilities.

Staff at NRC-regulated nuclear fuel cycle facilities are required to perform a detailed safety analysis to identify potential hazards, accident sequences, and other physical and human factors that could potentially compromise safety.

Licensees then assign items relied on for safety to the hazards identified to prevent potential accidents at a facility.

The inspection began Monday, and two inspectors from the NRC’s Region II office in Atlanta are at the Urenco USA plant.

Schneider Bold

Over several days, the inspectors will develop a timeline of the event and review the company’s root cause investigation. The inspection will also verify the company responded appropriately by their established emergency and safeguards contingency plans and has a plan to prevent a recurrence.

The inspection team will document their findings and conclusions in a public report issued within 45 days of the completion of the inspection.