In the incident, they drilled holes in the casing, inserted a lifting pin, and attached it to the crane’s auxiliary hoist line with a two-part sling and D-rings, according to a report with the Bureau of Safety and Environmental Enforcement (BSEE). The crane lifted the casing until it got stuck.
After setting the slips, the crew cut and removed a section, drilled new holes, and reinserted the lifting pin for another lift. They then used the crane’s main hoist to try to pull the stuck casing. The lifting pin ended up attached to the main block, and two workers stood next to the casing, ready to remove the slips when the casing moved upward.
Incident Findings
Among the findings in the incident include:
- Human errors led to the lifting pin failure and the worker’s injury.
- The crew installed a spool riser with an 11-inch inside diameter onto the wellhead, on top of a seal ring that was 11.44 inches in diameter. This stopped the casing from being pulled out.
- The crane operator lifted more than the approved safe lifting plan’s 24,255-pound limit and exceeded the lifting pin’s 60,000-pound safe working load. Tests suggest up to 102,000 pounds ended up applied to the pin during the incident.
- The crew did not place the D-rings of the sling right next to the casing; they were about 2 inches away. Procedures require the pull linkages to be as close as possible to reduce bending on the pin.
- The procedure used was for a drilling rig with a top drive and bails, not for a crane on a liftboat. It also wrongly listed the lifting pin’s capacity as 67,000 pounds, when the safe limit is 60,000 pounds.

Reenactment of the position of injured person and the other worker at time of incident.
Source: BSEE
Recommendations
To help prevent similar incidents in the future, BSEE recommends operators and contractors do the following:
- Operators should always check the load is free before starting crane operations to lift a work string during well abandonment.
- Never use a crane to pull or lift a load that is not free.
- Make sure the equipment used is clearly identified in procedures. Do not change procedures if they do not match the situation or equipment.
- Ensure the right equipment is available and installed during well abandonment. The lifting pin should be the correct length, since a pin that is too long can bend and fail early.
- Encourage workers to use stop work authority if they see or suspect unsafe conditions.
- Ensure proper rigging ends up used for all lifts and ends up installed as described in the lifting plan.
- Make sure procedures for lifting operations properly cite safe working loads for all rigging and devices.
- Make sure everyone is aware of hazards and keeps a safe distance from equipment during lifts.