Regulations are being proposed that would improve operational safety, human health, and environmental protections offshore.

The proposal would also attempt to providing clarity to industry regarding the Bureau of Safety and Environmental Enforcement’s (BSEE) review of projects that utilize new or unusual technology, including equipment used in high pressure and/or high temperature environments (HPHT).

BSEE considers novel technology to include equipment or procedures that have not been used previously or extensively under the anticipated operating conditions; have not been used previously in a particular Outer Continental Shelf (OCS) region; or that have operating characteristics outside the performance parameters established in 30 CFR part 250, a rule developed to increase safety as the industry moves to more challenging environments.

An HPHT environment is present when well conditions have pressures greater than 15,000 psia or temperatures greater than 350 degrees Fahrenheit.

“BSEE serves the American people as the lead federal agency for overseeing safe and environmentally responsible offshore energy production,” said BSEE Director Kevin Sligh. “The rules BSEE promulgates are critical to ensuring the offshore energy industry drives down risks of injury to offshore workers and protects the offshore environment, and this rule is particularly important for maintaining safe operations as the industry starts encountering more challenging operating conditions.”

Schneider Bold

This proposed rule would formally codify BSEE’s existing practice for reviewing and approving novel technology projects, including projects in HPHT environments, to provide clarity and certainty surrounding related requirements and BSEE processes.

This proposed rule would specifically:

  • Require submission of information in an order that provides operators and BSEE the ability to evaluate whether a new or unusual technology project is economically and operationally feasible.
  • Add specific equipment requirements, particularly for barriers, through new regulations and incorporation of industry standards.
  • Require independent third party (I3P) review of operator submissions, in certain cases, or provide BSEE with the ability to require I3P review, to ensure project viability and safety.

The proposed rule will publish in the Federal Register May 16. The 60-day public comment period closes July 15.

Pin It on Pinterest

Share This