A contract ended up signed to decommission eight orphaned pipelines in the Matagorda Island lease area, approximately 12 miles off the Texas coast.

The project will reduce pollution risks and improve offshore safety by decommissioning infrastructure that could interfere with navigation, commercial fisheries, and other current or future ocean uses.

On September 4, the Bureau of Safety and Environmental Enforcement (BSEE) awarded the five-year Indefinite Delivery/Indefinite Quantity contract to Chet Morrison Contractors, LLC, to conduct necessary on-site pipeline decommissioning activities.

On Sept. 13, BSEE awarded the first task order under the contract, for the Matagorda Island Area. The decommissioning contract ended up partially funded by President Biden’s Bipartisan Infrastructure Law.

“With this award, BSEE advances to the active pipeline decommissioning phase of the Matagorda Island area project,” said Kathryn Kovacs, Interior Deputy Assistant Secretary for Land and Minerals Management, who leads BSEE. “The funding provided by the Bipartisan Infrastructure Law is crucial to BSEE as we tackle orphaned infrastructure on the Outer Continental Shelf, which presents a serious hazard to safety and the environment.”

Schneider Bold

Last year, BSEE awarded contracts for the decommissioning of nine orphaned wells in the Matagorda Island lease area. The comprehensive project addresses urgent decommissioning needs, including securing wellheads, decommissioning pipelines with hazardous materials, and preparing the site for permanently sealing the wells.

While decommissioning on the Outer Continental Shelf is the obligation of the oil and gas industry, BSEE must ensure wells and infrastructure used in exploration, development, and production activities undertaken pursuant to the Outer Continental Shelf Lands Act end up decommissioned properly and in a timely manner to remove unnecessary hazards to safety, navigation, and the environment.

BSEE’s regulatory authority for Outer Continental Shelf decommissioning lies within 30 CFR 250, Subpart Q, Decommissioning Activities.

Overall, the Bipartisan Infrastructure Law allocated $250 million to clean up well sites in national parks, national forests, national wildlife refuges, and other public lands and waters, nearly $150 million of which ended up distributed over the past three years.